-
Fitness
for service evaluation was performed for the top bed of a stainless
steel reactor with the intent to calculate the maximum permissible
pressure differential allowed by the structural capacity of the bed. The
packed bed had 3 distinct stainless steel fabricated beams. The bed was
getting plugged during operation. This was causing significantly higher
pressure drop on the bed leading to very high stresses in the beams. The
intent was to shut down the reactor before the pressure drop reaches a
scenario causing the structural failure of the bed. The structural
calculations (per AISC code) were performed to check the stresses
in the beams, welds and the beam support grating. These structural
calculations were automated using MathCAD to calculate the
maximum allowable pressure drop through the bed for design case, upset
case and failure case. For each of these cases, the limiting pressure
drop for the three distinct structural beams and the associated grating
support was calculated. The design pressure drop through the reactor bed
was 100 psig. The maximum allowable pressure drop for the upset case was
specified to be 138 psig. At this pressure drop, all the design criteria
were satisfied and this pressure drop was safely permissible. The
maximum allowable pressure drop for the failure case was specified to be
158 psig. At this pressure drop, the code allowable stress criteria were
not satisfied and the structural components start to yield. Using the
pressure drop guidelines specified by these set of calculations, the
plant increased the safe operating time before the next shut down.
-
Fitness for service evaluation was performed for a tall vessel which had
severe corrosion for two courses of shell rings. The shell ring # 3
(from bottom) had corroded from original thickness of 0.375” to a
thickness of 0.135” and shell ring # 2 (from bottom) had corroded from
original thickness of 0.500” to current thickness of 0.270”. Hence, the
available section modulus in shell ring # 3 was not sufficient to carry
out the design wind loading for the vessel. This called for de-rating of
the vessel as well as providing an external support system which would
be capable of carrying the design wind load. The intent was that the
vessel would be operated for a few months only and the corrosion rates
would be controlled by modifying the process. The following three
recommendations list the possible choices for reviving the vessel:
1.
Replace shell ring # 3 and shell ring # 2 with new shell plates
of 0.375” thickness and 0.500” thickness respectively.
2.
Install a 9’-0” wide (Min.) X 3/8” thick plate (Material:
SA-516-70) to cover shell ring # 3 (from bottom) with 3/8” fillet welds.
This will cover the corroded shell ring # 3 and will extend a minimum of
6” beyond circumferential seam in either direction.
3.
Install six (6) structural supports (60°
apart from each other) around the vessel covering the shell ring # 3 and
going approximately 2’ beyond the horizontal circumferential seams. The
structural design was based on the availability of the I-beams (W6X15,
Material: SA-36) in the scrap yard. The final size of each of these
supports was calculated per structural engineering calculations in
accordance with AISC. This design was meant to take care of the
design wind loading only and not meant to provide any additional
corrosion allowance or additional pressure rating for the vessel. Based
on the thickness loss for the shell ring, the vessel must be de-rated
from 125 psig @ 650 °F to 54 psig @ 650
°F.
The
first two alternatives were not implemented due to time constraint and
delay in material procurement. The third alternative was the preferred
choice because the plant could quickly make the vessel fit for service
with the specified repairs. This was considered short term fix till the
next turnaround.
Go
to Structural Engineering / Analysis Page |